Helpng to make the dream a reality

Nov 2014 to Oct 2017
- Volunteered to oversee Construction of a New Hospital to replace a 27+ year old facility staffed and operated by Dominicans. I spent 3 years on behalf of the many donors to the REVOLUTION campaign - a 4.5 Million Dollar campaign to fund this project.
August 2017 to September 2018
Work ceased while Tax issues resolved
Oct 2018
Working as project consultant to help get this wonderful project completed.

Friday, May 27, 2016

Challenges behind us, good stuff ahead


It has been a difficult couple of months. We made the hard decision to ask our builder / engineer to step down and no longer be involved with the project. It was a very disappointing step to have to take, but a necessary one. 
Money is tight, we have not met our campaign goal and so we must watch every expense and spend as frugally as we can. In spite of this being the case, our builder just was not on board with us in this regard. I think he is like most everyone in the DR who believes the organizations from the USA have all of the money in the world and will pay whatever is necessary. It is just the common opinion here. 
Frank has explained to several potential suppliers and subs that Solid Rock is not that American organization that has a large shiny building in a downtown somewhere. Solid Rock is a single room in a young couple's home, and there are only two employees there, there is no "national headquarters". It is a concept that many Dominicans just do not comprehend, it is that simple. The USA is considered  'the land of opportunity, the land of abundance, it can provide all that is needed for a project here in the DR' - well, not in our case. Our generous donors are many, but we still need more money in order to make this dream a reality, and it will happen.

So we are being as deliberate as needed in order to see that the money everyone has so generously provided can go as far as it can.

I am so very proud of Solid Rock being ranked #47 out of over 8,300 non-profit organizations AND being on three of their "top ten" lists. It is a nice recognition of the hard work our board of directors (both now and in the past) has done to keep the focus on what our purpose is about. All of the wonderful things that have happened here are the result of support from people like you - those who have donated hard-earned money to Solid Rock and/or those who have donated their money, time and talents (often giving up precious vacation time) and traveling to the DR, serving the people here. So if you stay focused on what you want to do, do it well, accomplish it only thru the generous hands of donors and volunteers, and keep after it for 26+ years ... it works. And it works very effectively. This is accomplishing a little bit of what Jesus asked us to do - SERVE OTHERS. 
See more info - click this: Charity Navigator Site

So to everyone who has been a part of this wonderful journey since 1990 and even earlier, THANK YOU.


I am excited that we are lining up getting over 30,000 block delivered so that we can start getting some walls rising from the ground. I hope that by the end of summer there is a building looking for a roof! At the same time we will be tackling the plumbing drain lines and then other conduits and pipes that will be located under the floor.

We have asked an engineer who has been acting as consultant with the the project to begin a 3 month trail as "head" engineer. He has been SUPER HELPFUL over the past year serving in a consulting role and has recommended most of the suppliers and laborers we have used. I am very excited to have him "running the ship" knowing that he is very capable and also very conscious that money is critical and making things as efficient as possible is a necessity.

So I hope this is the last of the "tough news" I need to share. Good things never come easily, and I'm pretty sure some bible verses point this out to us ... :).

Never be lazy, but work hard and serve the Lord enthusiastically. Rejoice in our confident hope. Be patient in trouble, and keep on praying.     Romans 12:11-12 
KEEP ON PRAYING






Friday, May 6, 2016

What is this project?


Below is the FLOOR PLAN and it shows what each area of the facility will provide:




We are now about to start building the walls of the clinic, and it occurred to me that perhaps you do not really know what this new facility will offer. It will be a huge jump from what has been provided at the current 13,000 ft2 clinic vs this new building of more than 46,000 ft2

Here is a summary:



Services to be offered

·      Pre-Op - 4 beds
·      Post-Op - 4 beds
·      3 Operating Rooms
·      1 C-Section Operating Room
·      1 Gastroenterology
·      Intensive Care - 4 beds
·      Maternity - Natural and C-Section delivery
-       includes 4 beds for Pre & Post Delivery
-       includes Neo-Natal Intensive Care
·      Emergency Room
-       Including fully equipped Ambulance
-       Paramedics
·      Mobile X-Ray
·      Cardiology
·      Sonography, Mamography

·      Dentistry (includes X-Ray)
·      OB/Gyn
·      Lab
·      Pharmacy
·      Psychological Counseling
·      Child Nutrition Education
·      Morgue
·      8 Private Rooms
·      2 Private Suite Rooms
·      

3 Semi Private Rooms (6 total beds)

























THANK YOU FOR YOUR PRAYERS AND SUPPORT.





Tuesday, April 12, 2016

Just about ready to begin Drain Lines!



A beautiful view high atop the mountains

We've made it.

We are finally to the point where you will start seeing walls going up soon. You will hear me cheer when we begin this significant phase ...  !

First we will begin the process of installing drain pipes - we have a limited space to run them and achieve a proper slope so this will need to be done carefully. Once we have a good start on this we will start block work. 

I always feel I must stress that our #1 concern is that all work is done efficiently, at the lowest cost we can negotiate, and with the best prices on materials. If we spend extra time assuring that this happens, time will just have to wait. The precious money we have received from so many amazing, supportive and wonderful organizations, families and individuals is being spent as frugally as possible.

Sorry for the length of this video, but I spent time bringing you up to date on the entire site, probably in too much detail ...



Thanks for your continuing support and prayers. God's amazing timing continues to be at work here as we make slow but steady progress.

Here are a few pictures:

A sad day, our Skid Steer went back to its home in Santo Domingo.


A Dominican house

and you have to appreciate the sunsets here ...


Monday, March 21, 2016

Fill & Compaction of Platea almost done

We are close to completing this labor-intensive phase. 16 columns will be formed and poured, then we can finish this fill and compaction. 

Here is a video showing what things look like:

The next steps will be:
1) installing drain lines in this material which will require digging ditches with the proper slope for good drainage in the pipes. 
2) start laying block walls!

Happy Easter!




Thursday, March 3, 2016

46,150 square feet

Yep, It is a big building, just ask the guys having to spread and compact this huge expanse!



We are continuing to fill and compact, a slow labor-intensive process.



 The team from Roanoke worked on the south wall prepping the grade beam for more block to be laid!

It was really great to have some of our church family here, the medical folks did their typical amazing work helping those in need. We had a very nice communion service Wednesday night at Prince of Peace.  


Thanks for your prayers and support for the project and for the almost 1,000 people who spend hard earned money and devote a week out of their lives to serve others here in the San Juan region.

As each has received a gift,
use it to serve one another,
as good stewards of God's varied grace
1 Peter 4:10









Saturday, February 13, 2016

Next Phase has Started - Fill and Compacting the Platea





Site as of Feb 12th


We have started the process of filling and then compacting the platea. This will be a tedious phase and require a lot of manual labor and shovel work. Each room will need to be filled and then compacted 3 times in order to properly compact the fill because this is what the floor slab will eventually rest on.

A heavy rain left over an inch of water
  The amazing volunteer teams have made great progress on the south security wall - this will be very helpful for jobsite security in the short term and property security in the future. 

The south wall is moving along!

Saw a guy using this wheelbarrow - one stable wheelbarrow!
Lifetime Guarantee - WILL NOT TIP OVER!

As always, thank you for your support and prayers. Many challenges remain but good progress is being made. 

Saturday, February 6, 2016

Block is in place, columns being formed and poured.

We are done laying 2 courses of block, 
next will be columns.

who needs a pickup Truck?!

video below:

Thanks for your prayers and support!