Helpng to make the dream a reality

Nov 2014 to Oct 2017
- Volunteered to oversee Construction of a New Hospital to replace a 27+ year old facility staffed and operated by Dominicans. I spent 3 years on behalf of the many donors to the REVOLUTION campaign - a 4.5 Million Dollar campaign to fund this project.
August 2017 to September 2018
Work ceased while Tax issues resolved
Oct 2018
Working as project consultant to help get this wonderful project completed.

Tuesday, July 5, 2016

update July 5 2016

Some pictures of work on the building over the last few days.



What you see when first driving onto the property

Standing at the southeast corner, looking at the large conference room and exam rooms

Setting up to start 3 more courses of block  on the east wall looking north
Taken from atop the warehouse looking west

Mixing mortar mix for the block masons

Sifting sand that will be used by the masons

Our diesel mixer is used to mix the concrete that is poured into the block cells

The ER area

Mixing mortar for the ER area

A bunch of mortar waiting to be used in the west part of the building near the kithen

Building walls for the private room section
 And Finally, a time lapse from work on Saturday, July 2nd.



Thursday, June 30, 2016

Going Up

The block masons are moving along very well.




As they lay block we are locating doors, windows and plumbing pipe locations. Electrical locations will utilize the voids in the block that are not filled with concrete. 

Here is a time lapse from this morning:



Will post another video soon!


Saturday, June 18, 2016

Wall update June 18

Work is moving along with much to do. We have three subs each with their own crews working on the block work, so there are about 50 workers onsite. They are laying a bunch of block daily, so we have been working hard to stay ahead of them laying off doors and plumbing locations and confirming final locations and information of many details. Everyone is working well together, Our team of three engineers are overseeing the work and are onsite the entire day, checking that work is properly done.





Here is a quick video of the site from above ...



Stay tuned for more good news!
Keep up the prayers and support, Thanks so much!

Tuesday, June 14, 2016

The WALLS are underway!

It has been a long time coming, but on Monday, June 13, 2016 we started building the walls. We are officially above the foundation walls!

Mixing mortar - powered mixer optional


















Here is a short video from Monday afternoon:




And some other pics ...


Some of the team from Pine Hills assembling a column

A heavy rain offers a good source of water for mortar mixing


End of the day on Monday, nice.




Thursday, June 9, 2016

Lets get this started ... WALLS!

I'm excited!



We are at the end of a slow period during which we changed engineer/builder so that construction will go as efficiently as possible. It was a difficult decision, but necessary. 

My optimism is strong - there is a new level of commitment and drive to ensure that that the project happens as efficiently as possible.  Frank and I feel like the team we envisioned is now in place. 


Masons are lined up, block is arriving, the plumbing and electrical engineers are finalizing details ... we are like the space shuttle that is T minus 10 seconds and counting. I can't wait!  Here is a little video summary.













T minus 9 ...


WAIT! - Don't close this without a short prayer!

ok, thanks. :)



Friday, May 27, 2016

Challenges behind us, good stuff ahead


It has been a difficult couple of months. We made the hard decision to ask our builder / engineer to step down and no longer be involved with the project. It was a very disappointing step to have to take, but a necessary one. 
Money is tight, we have not met our campaign goal and so we must watch every expense and spend as frugally as we can. In spite of this being the case, our builder just was not on board with us in this regard. I think he is like most everyone in the DR who believes the organizations from the USA have all of the money in the world and will pay whatever is necessary. It is just the common opinion here. 
Frank has explained to several potential suppliers and subs that Solid Rock is not that American organization that has a large shiny building in a downtown somewhere. Solid Rock is a single room in a young couple's home, and there are only two employees there, there is no "national headquarters". It is a concept that many Dominicans just do not comprehend, it is that simple. The USA is considered  'the land of opportunity, the land of abundance, it can provide all that is needed for a project here in the DR' - well, not in our case. Our generous donors are many, but we still need more money in order to make this dream a reality, and it will happen.

So we are being as deliberate as needed in order to see that the money everyone has so generously provided can go as far as it can.

I am so very proud of Solid Rock being ranked #47 out of over 8,300 non-profit organizations AND being on three of their "top ten" lists. It is a nice recognition of the hard work our board of directors (both now and in the past) has done to keep the focus on what our purpose is about. All of the wonderful things that have happened here are the result of support from people like you - those who have donated hard-earned money to Solid Rock and/or those who have donated their money, time and talents (often giving up precious vacation time) and traveling to the DR, serving the people here. So if you stay focused on what you want to do, do it well, accomplish it only thru the generous hands of donors and volunteers, and keep after it for 26+ years ... it works. And it works very effectively. This is accomplishing a little bit of what Jesus asked us to do - SERVE OTHERS. 
See more info - click this: Charity Navigator Site

So to everyone who has been a part of this wonderful journey since 1990 and even earlier, THANK YOU.


I am excited that we are lining up getting over 30,000 block delivered so that we can start getting some walls rising from the ground. I hope that by the end of summer there is a building looking for a roof! At the same time we will be tackling the plumbing drain lines and then other conduits and pipes that will be located under the floor.

We have asked an engineer who has been acting as consultant with the the project to begin a 3 month trail as "head" engineer. He has been SUPER HELPFUL over the past year serving in a consulting role and has recommended most of the suppliers and laborers we have used. I am very excited to have him "running the ship" knowing that he is very capable and also very conscious that money is critical and making things as efficient as possible is a necessity.

So I hope this is the last of the "tough news" I need to share. Good things never come easily, and I'm pretty sure some bible verses point this out to us ... :).

Never be lazy, but work hard and serve the Lord enthusiastically. Rejoice in our confident hope. Be patient in trouble, and keep on praying.     Romans 12:11-12 
KEEP ON PRAYING






Friday, May 6, 2016

What is this project?


Below is the FLOOR PLAN and it shows what each area of the facility will provide:




We are now about to start building the walls of the clinic, and it occurred to me that perhaps you do not really know what this new facility will offer. It will be a huge jump from what has been provided at the current 13,000 ft2 clinic vs this new building of more than 46,000 ft2

Here is a summary:



Services to be offered

·      Pre-Op - 4 beds
·      Post-Op - 4 beds
·      3 Operating Rooms
·      1 C-Section Operating Room
·      1 Gastroenterology
·      Intensive Care - 4 beds
·      Maternity - Natural and C-Section delivery
-       includes 4 beds for Pre & Post Delivery
-       includes Neo-Natal Intensive Care
·      Emergency Room
-       Including fully equipped Ambulance
-       Paramedics
·      Mobile X-Ray
·      Cardiology
·      Sonography, Mamography

·      Dentistry (includes X-Ray)
·      OB/Gyn
·      Lab
·      Pharmacy
·      Psychological Counseling
·      Child Nutrition Education
·      Morgue
·      8 Private Rooms
·      2 Private Suite Rooms
·      

3 Semi Private Rooms (6 total beds)

























THANK YOU FOR YOUR PRAYERS AND SUPPORT.