A panorama photo of the site - photo taken soon after a heavy thunderstorm came through. View looks from southeast to northwes with the highway on the right side (NW direction). |
89 columns are being fabricated using rebar. These require 10 20' pieces of 1/2" rebar and are tied together with 3/8" rebar. These will be positioned in place when rebar is being placed and tied together in the platea/foundation.
And because we want to be well grounded ...
Thermite Welding: Serious Soldering of the grounding wire - check out the video below: FIRE IN THE HOLE! |
Currently a grounding system is being put in place that will ground all electrical devices, minimize the chances of static electricity and offer the best grounding protection possible for the workers and patients as well as the electronic equipment that will be in the building. This includes a thick copper wire that runs the perimeter of the platea and is using a process called Exothermic or Thermite Welding which makes an excellent connection between the copper wire and the 10' (deep) copper grounding rods spaced around the building.
A closeup of the form work and electrical ditch. This ditch runs the perimeter of the platea and is for a thick copper cable that has 10' grounding rods evenly spaced around the platea. |
A 2 minute video of simply pounding a 10' ground rod
into a compacted fill.
Making the connection using a
thermite welding technique
(very intense HEAT/FIRE!):
thermite welding technique
(very intense HEAT/FIRE!):
Pretty cool