Helpng to make the dream a reality

Nov 2014 to Oct 2017
- Volunteered to oversee Construction of a New Hospital to replace a 27+ year old facility staffed and operated by Dominicans. I spent 3 years on behalf of the many donors to the REVOLUTION campaign - a 4.5 Million Dollar campaign to fund this project.
August 2017 to September 2018
Work ceased while Tax issues resolved
Oct 2018
Working as project consultant to help get this wonderful project completed.

Thursday, November 26, 2015

Happy Thanksgiving!

  Happy Thanksgiving to everyone! We have had a fun day so far overloading the kitchen with many dishes being prepared with unlimited awesome help from the Ohio Northern team!
  I hope everyone has a wonderful day acknowledging all that we have in our lives from family, friendships, comforts, food, and God our Father. 
  Be sure and eat too much! 
 

All Turkeys who visit the site are required to wear hardhats

Birds on the Grill!
Laura took this picture of a Poinsettia TREE near El Cercado!


Some of the girls from Ohio Northern making CARABOLA juice!

Happy Thanksgiving from the jobsite!

Stacy, Isabelle and Courtney got a bunch of vegetable and flower seeds planted at the jobsite
stoking the coals in the grill

Stacy's pecan pies - not many of these here in the DR !!


Wednesday, November 18, 2015

As each has received a gift, use it to serve one another, as good stewards of God's varied grace. 

Peter ch4,v10 


One Year Anniversary

  One year ago we were celebrating Ground-Breaking, a year later the site has had a serious face-lift - removing 1/2 a meter of topsoil and adding over 2 meters of a compacted fill material. This stable base is what will support the Clinic, the closest thing we can do to provide a Solid Rock!
Ground Breaking Ceremony: November 18, 2014
Site as of November 18, 2015

  We have tied over 120 miles of rebar in the foundation and it is almost ready to have over 1,200 cubic meters of concrete placed - that is over 200 concrete trucks! We have scheduled this work for the second week of December.
  Once this is done, two courses of concrete block will be laid for all of the walls, so "walking the clinic" will then be possible.
  Next week is Thanksgiving - What wonderful timing that we can celebrate that this project is rising from the ground!

  Thank you for your prayers and support!

"we make a living by what we get, but we make a life by what we give."



  






Saturday, November 7, 2015

Platea / Foundation Work is moving along - pictures and videos

Its November 7th, the rebar work for the platea started about 3 weeks ago, and it is ahead of schedule. 


Most of the structural rebar is in place, and over 90 of the 12' columns. Much work remains, specifically setting the"bastones" - these are the pieces of rebar that will project up into all of the walls to anchor them to the platea slab. They need to be located very accurately.


First - a quick video showing 
what the site looks like today:



Second - a video showing details
 of the rebar construction:



Finally -The picture below was taken
in between the two layers of rebar




   The rebar work should be completed by the end of November, and we hope to schedule the concrete work for early December!
   Once the concrete is in place, a "normal" building process will begin with concrete block being laid to define all of the walls and then plumbing and other under-floor pipes being installed.


Thanks for your prayers and support!


-