Helpng to make the dream a reality

Nov 2014 to Oct 2017
- Volunteered to oversee Construction of a New Hospital to replace a 27+ year old facility staffed and operated by Dominicans. I spent 3 years on behalf of the many donors to the REVOLUTION campaign - a 4.5 Million Dollar campaign to fund this project.
August 2017 to September 2018
Work ceased while Tax issues resolved
Oct 2018
Working as project consultant to help get this wonderful project completed.

Sunday, April 16, 2017

April 2017 update - with some architectural flair!

The second of our Seven Sections is formed, now the Rebar workers will be busy assembing and installing the rebar for the beams and roof slabs in this section. 
On the section we completed the roof on last month we now have an architectural feature! Yes, the "swoop" adds some flair at a low cost - check it out in the pictures!

Meanwhile, we have completed our main Septic Tank, Completed our neighborhood bridge across the canal, are starting on the 30,000 gallon Water Cistern and getting our 140 meter main drain line in the ground. 

We plan to complete the roof concrete on this next section near the end of the month ... stay tuned!

It is a busy place and things are progressing well.


The Lobby has the form-work in place for the Roof Slab. 

A detail (work underway!) to be sure water is not an issue -  showing pipes that will allow a/c lines to run down into the room below but not directly penetrate the roof or be installed where they would be visible.

A full panorama of the front of the building

The Lobby is in the center with the section with a completed Roof Slab to the Left (see the "swoop"?). The Emergenct Room is to the Right - this section will have a higher wall height.


The Consult Section with our "swoop" / "Architectural Feature" - modern !?




Thank you for your interest, sharing our story and most importantly for your prayers and support.


Wednesday, April 5, 2017

April 2017 Video Update

Here is a video update after getting the first roof slab completed ...