On the section we completed the roof on last month we now have an architectural feature! Yes, the "swoop" adds some flair at a low cost - check it out in the pictures!
Meanwhile, we have completed our main Septic Tank, Completed our neighborhood bridge across the canal, are starting on the 30,000 gallon Water Cistern and getting our 140 meter main drain line in the ground.
We plan to complete the roof concrete on this next section near the end of the month ... stay tuned!
It is a busy place and things are progressing well.
The Lobby has the form-work in place for the Roof Slab. |
A full panorama of the front of the building |
The Lobby is in the center with the section with a completed Roof Slab to the Left (see the "swoop"?). The Emergenct Room is to the Right - this section will have a higher wall height. |
The Consult Section with our "swoop" / "Architectural Feature" - modern !? |
Thank you for your interest, sharing our story and most importantly for your prayers and support.