Helpng to make the dream a reality

Nov 2014 to Oct 2017
- Volunteered to oversee Construction of a New Hospital to replace a 27+ year old facility staffed and operated by Dominicans. I spent 3 years on behalf of the many donors to the REVOLUTION campaign - a 4.5 Million Dollar campaign to fund this project.
August 2017 to September 2018
Work ceased while Tax issues resolved
Oct 2018
Working as project consultant to help get this wonderful project completed.

Thursday, June 9, 2016

Lets get this started ... WALLS!

I'm excited!



We are at the end of a slow period during which we changed engineer/builder so that construction will go as efficiently as possible. It was a difficult decision, but necessary. 

My optimism is strong - there is a new level of commitment and drive to ensure that that the project happens as efficiently as possible.  Frank and I feel like the team we envisioned is now in place. 


Masons are lined up, block is arriving, the plumbing and electrical engineers are finalizing details ... we are like the space shuttle that is T minus 10 seconds and counting. I can't wait!  Here is a little video summary.













T minus 9 ...