Helpng to make the dream a reality

Nov 2014 to Oct 2017
- Volunteered to oversee Construction of a New Hospital to replace a 27+ year old facility staffed and operated by Dominicans. I spent 3 years on behalf of the many donors to the REVOLUTION campaign - a 4.5 Million Dollar campaign to fund this project.
August 2017 to September 2018
Work ceased while Tax issues resolved
Oct 2018
Working as project consultant to help get this wonderful project completed.

Tuesday, July 12, 2016

Block Walls update July 12 2016


70,000 block are now onsite and most are laying in walls! Our three mason crews are each finishing up their section of the building. Cleanup and filling of the block cells with concrete continues. 
We will now begin forming the beams that will span doorways, windows and the skylight-type structures so these can then be filled with concrete. 
During this same time the plumber can begin digging properly sloped ditches for the many drain pipes and then install these pipes now that the 40+ masonry workers are done with this portion of their work.




Here is are a couple of videos, one showing a brief overview of the building site and the work by volunteers and another is a one minute tour - hang on tight!

Around the Site:





A one minute walk-thru:







Thanks for the prayers and support - 
both greatly appreciated!

No comments:

Post a Comment