This will be a picture update.
-Plumbing rough-in is completed.
-Government modifications completed.
-Electrical rough-in is underway.
-Rebar fabrication is underway.
-Door Headers are underway.
-Main Septic Tank only needs
coconut husks(yep) and a top.
A small bathroom added to the right of one of the main nursing stations |
Doorways for patient access have been widened |
Location for a panel box for the "consult" section of the building. |
Rough-in boxes for wall switches - these conduits run UP to above the dropped ceilings where we will run the wiring to lighting and panel boxes. |
Electrical Rough-in work underway. Here they are cutting in a slot for an outlet. |
Gadget used to bend the rebar |
Rebar assemblies ready to go |
Rebar "cages" are used to assemble long rebar assemblies - these will be used for our "vigas" |
A water level is used to set the bottom heights of the header forms |
A carpenter hammering a form in place |
Forms are in place for the many headers that span doorways. |
|
Forming a door header |
A door header and rebar assembly ready for concrete. |
filling the header - one bucket at a time. |
The main septic tank is ready for a top once coconut husks are added that will filter the water before it leaves the tank. |
Many things are underway that don't have the visual impact that 70,000 block do, but we are working on the details that create a functional building.
Good stuff.