Helpng to make the dream a reality

Nov 2014 to Oct 2017
- Volunteered to oversee Construction of a New Hospital to replace a 27+ year old facility staffed and operated by Dominicans. I spent 3 years on behalf of the many donors to the REVOLUTION campaign - a 4.5 Million Dollar campaign to fund this project.
August 2017 to September 2018
Work ceased while Tax issues resolved
Oct 2018
Working as project consultant to help get this wonderful project completed.

Thursday, January 26, 2017

January 2017 Update - picture summary

This will be a picture update. 

-Plumbing rough-in is completed.
-Government modifications completed. 
-Electrical rough-in is underway.
-Rebar fabrication is underway.
-Door Headers are underway.
-Main Septic Tank only needs
 coconut husks(yep) and a top.


Water pipes are in place and we will clean away any debris from
the pipes and surround with sand - after all have been pressure tested.
This is in one of the lab rooms where HOT WATER will also be
available. Most sinks will only have cold water - the norm in the DR.

A small bathroom added to the right
of one of the main nursing stations

Doorways for patient access have been widened

















Location for a panel box for the "consult" section of the building.

Rough-in boxes for wall switches - these conduits run UP
to above the dropped ceilings where we will run
 the wiring to lighting and panel boxes.

A completed outlet installation - wiring will be added later and
 run below the floor slab. Having these in place will allow
 plasterers to finish the walls, the floors will be done after the wall plaster.

Electrical Rough-in work underway.
Here they are cutting in a slot for an outlet.




Gadget used to bend the rebar



Rebar assemblies ready to go




Rebar "cages" are used to assemble long rebar assemblies
 - these will be used for our "vigas"
A water level is used to set the
bottom heights of the header forms







A carpenter hammering a form in place




      
Forms are in place for the many headers that span doorways.

Looking down the Laboratory hallway
with forms in place for the headers.
Forming a door header


A door header and rebar assembly ready for concrete.
Mixing the concrete for the door headers.
filling the header - one bucket at a time.






















The main septic tank is ready for a top once
coconut husks are added that will filter the
water before it leaves the tank.

Many things are underway that don't have the visual impact that 70,000 block do, but we are working on the details that create a functional building. 
Good stuff.

Thanks for your prayers and financial support, please consider helping us with a donation if you have not already done so.